Independent study aid. Not affiliated with or endorsed by NCEES. Always verify against the current NCEES exam specifications and reference handbook.

FE section 14 of 16 · free theory

Construction Engineering

Schedules, quantities, equipment, and earthwork — the Construction slice of the FE Civil exam, built around calculations you can do by hand in a few minutes.

FE foundation · Construction (8–12)

Take the free 5-question mini-quiz ↓

CPM scheduling: forward pass, backward pass, float

The critical path method turns a list of activities and dependencies into a project duration. Run two passes over the network:

Forward: ES = max(EF of predecessors), EF = ES + duration   Backward: LF = min(LS of successors), LS = LF − duration

Total float = LS − ES = LF − EF    Free float = min(ES of successors) − EF

ES, EFearly start / early finish
LS, LFlate start / late finish
Total floathow long an activity can slip without delaying the project
Free floathow long it can slip without delaying any successor

The critical path is the longest-duration path through the network — its activities have zero total float, and its length is the project duration. Gantt (bar) charts show the same schedule as horizontal bars over time; they display timing and overlaps but not dependencies, which is why CPM networks sit underneath them.

Worked example Forward/backward pass and critical path

Given:

  • A (3 days) precedes B (4 days) and C (5 days); B and C both precede D (2 days).

Solution:

  1. Forward pass: A: ES 0, EF 3. B: ES 3, EF 7. C: ES 3, EF 8. D: ES = max(7, 8) = 8, EF 10. Project duration = 10 days.
  2. Backward pass: D: LF 10, LS 8. B: LF 8, LS 4. C: LF 8, LS 3. A: LF = min(4, 3) = 3, LS 0.
  3. Floats: A: 0; B: 4 − 3 = 1 day; C: 0; D: 0. The zero-float path A→C→D is critical (3 + 5 + 2 = 10 days). B can slip 1 day without affecting the finish.

Answer: Project duration 10 days; critical path A→C→D; activity B has 1 day of total float.

Estimating and quantity takeoff

Estimating starts with takeoff: measuring quantities from the drawings, then pricing them. The exam-level mechanics are unit conversions and careful arithmetic rather than pricing strategy:

Volume (CY) = Volume (ft³) / 27    1 CY = 27 ft³

Bank CY (BCY)material in its natural, in-place state
Loose CY (LCY)material after excavation (swelled)
Compacted CY (CCY)material after placement and compaction (shrunk)

Equipment is rated in loose cubic yards per hour; earthwork pay quantities are usually bank (in place). Convert with the swell factor: LCY = BCY × (1 + swell). A typical soil swell of 25% means 100 BCY becomes 125 LCY.

Equipment productivity

Equipment output is bucket (or blade) capacity divided by cycle time, scaled to a working hour. The 50-minute hour (job efficiency 50/60 ≈ 0.833) is the standard allowance for non-productive time:

Production (LCY/h) = (60 × capacity (LCY) × efficiency) / cycle time (min)

Trucks required = truck cycle time / loader cycle time  (round up)

Cycle timeload + haul + dump + return (and spot/wait) for the controlling unit, min
Efficiency50-min hour → 0.833 unless stated otherwise

Trucks are sized so the loader never waits: enough trucks to cover one full truck cycle per loader cycle, rounded up — 7.2 trucks means 8 trucks. Production is always governed by the slowest link: quote the loader or the hauler rate, whichever is lower.

Worked example Dozer production in loose and bank yards

Given:

  • Dozer blade capacity 5 LCY, cycle time 1.2 min, 50-minute hour, soil swell 25%.

Solution:

  1. Production = 60 × 5 × (50/60) / 1.2 = 250 / 1.2 = 208.3 LCY/h.
  2. Convert to bank yards: 208.3 / 1.25 = 166.7 BCY/h.

Answer: ≈ 208 LCY/h (≈ 167 BCY/h after 25% swell).

Earthwork volumes

Volumes between two cross-sections come from the average end area method; the prismoidal formula adds the mid-section for a better answer when sections vary non-linearly:

V = L (A1 + A2) / 2    V = L (A1 + 4Am + A2) / 6

Vvolume, ft³ (divide by 27 for CY)
Ldistance between the end sections, ft
A1, A2end cross-section areas, ft²
Ammid-section area, ft² (prismoidal only)

Prismoidal is exact for prismoids and a better approximation when the mid-section differs from the average of the ends. If Am happens to equal (A1 + A2)/2 — sections varying linearly — the two methods agree exactly.

Worked example Average end area vs prismoidal

Given:

  • Two sections 100 ft apart: A1 = 120 ft², A2 = 180 ft², mid-section Am = 145 ft².

Solution:

  1. Average end area: V = 100 × (120 + 180)/2 = 15,000 ft³ = 15,000/27 = 555.6 CY.
  2. Prismoidal: V = 100 × (120 + 4 × 145 + 180)/6 = 100 × 880/6 = 14,666.7 ft³ = 543.2 CY.
  3. The mid-section is leaner than the average of the ends, so prismoidal correctly trims the volume by about 12 CY.

Answer: 555.6 CY by average end area; 543.2 CY by prismoidal.

Cost control concepts

The exam tests the vocabulary of tracking, not full earned-value arithmetic. Planned value is what the schedule said you would spend; earned value is what the completed work was worth; actual cost is what you really spent. Cost variance (earned − actual) and schedule variance (earned − planned) tell you, at a glance, whether the job is over budget, behind schedule, or both — and the exam usually asks only which of the two is true and in which direction.

Free 5-question mini-quiz

Construction Engineering

Choose your answer, then check it to see the result and explanation. US customary units are used throughout, as on the exam.

1. Activities: A (2 days) precedes B (3 days) and C (4 days); B and C precede D (2 days). What is the total float of activity B?

2. Compared with a CPM network diagram, what is the main limitation of a Gantt (bar) chart?

3. Two cross-sections 100 ft apart have areas of 200 ft² and 260 ft². What is the earthwork volume by the average end area method?

4. A dozer has a 4-LCY blade and a 1.0-minute cycle time. Using a 50-minute hour, what is its production?

5. A loader fills a truck every 2.5 minutes, and one truck's full load–haul–dump–return cycle takes 20 minutes. How many trucks keep the loader continuously busy?

Ready for the complete 110-question rehearsal?

Step up from this five-question taster to the flagship 5-hour-20-minute timed simulation across every FE Civil section, with detailed solutions.